Return to Loughborough University for Major Heat Network Reconfiguration

Continuing our 25-year relationship by reconfiguring the heat network to enable the construction of a new student accommodation block.

University campuses constantly evolve to meet changing teaching and learning needs. This often requires reconfiguring heat networks to connect new buildings, reroute pipework, and disconnect buildings planned for demolition.

Loughborough University is currently adding 552 student beds on land that previously housed the Graham Oldham and Chemistry buildings. To support this, Vital Energi rerouted district heating pipework away from a car park that will be developed for new student accommodation.

This work was essential for the campus redevelopment. It involved draining the pipework, creating a new section, and shutting down the heat network to connect the new section of district heating to the existing network.

Capping some of the existing pipework as part of the reconfiguration works.

Solution detail

Vital Energi have been partnering with Loughborough University for over 25 years and have installed over 7km of district heating pipework, helping their heating network evolve to meet the changing needs of their campus.

Non-Destructive Testing of the welds ensures the highest quality of the jointing system which is a key element for ensuring longevity.

Solution detail